Indicative project timeline

We submitted our DCO application to the Secretary of State on 31 May 2024, it was accepted for examination on 28 June 2024 and development consent was granted on 1 December 2025.

The six-month examination period included a preliminary meeting, multiple issue specific hearings and a total of eight examination deadlines. These sessions covered a wide range of issues and involved helpful discussions between us, the Examining Authority and our stakeholders. The public, statutory consultees and interested parties were given the opportunity to give evidence to the Examining Authority.

The application was granted development consent by the Secretary of State for Energy Security and Net Zero on 1 December 2025.

We anticipate commencing construction in 2027 at the earliest and expect the Morecambe Offshore Windfarm generation assets to be operational by 2030.

Indicative project timeline

2021

  • Non-statutory engagement begins (introductory meetings and website launch)

2022

  • Non-statutory consultation

    Ongoing technical and environmental survey and assessment work

2023

  • Statutory consultation

    Ongoing technical and environmental survey and assessment work

2024

  • Application submitted for a Development Consent Order (DCO) - May 2024

    Application accepted for examination – June 2024

    Pre-examination period – June to October 2024

    Relevant representation period open – July to August 2024

    Examination commenced – October 2024

2025

  • Examination concludes - April 2025

    Development consent for Morecambe Offshore Windfarm Generation Assets granted - 1 December 2025

2026

  • Expected Final Investment Decision

2027

  • Earliest anticipated start of construction

2030

  • Expected Commercial Operation Date

Contact us

Should you have any queries, please get in touch with us using one of the methods below: