Indicative project timeline

The Secretary of State granted Morgan Generation Offshore Wind Farm development consent on 29 August 2025.

Indicative project timeline

May/June 2023

  • Statutory consultation on the Morgan Offshore Wind Project

April 2024

  • Application submitted to the Planning Inspectorate for a development consent order (DCO)

May 2024

  • Application accepted for Examination

March 2025

  • Examination for the project closed

Late 2025

  • Development consent granted in Q3 2025

2029

  • Potential to connect to the National Grid